A Completed RFI With Problem And Resolution Data Entered.
Problem: doors were delivered 2 inches too tall – need repair / replacement.
This change requires extra work – therefore a project variance exists. Since faulty supplier material is involved a back charge (BCN) is also appropriate. 
An FCR is written to authorize extra work.
The RFI documents the change and how it was resolved!
A variance, back charge, and field change complete the resolution of the change. All created simply from the VN form